Phoenix Residential Building Permit Requirements: What You File and the Review Steps

A new home in Phoenix needs a building permit before any work starts. You submit proposed building plans using the Residential Plan Submittal Plan Review Checklist, plus a Construction Permit/Plan Review Application, two sets of plans and calculations, and a plot plan. Staff reviews for code compliance, then issues the permit after fees are paid.

Updated June 29, 2026 4 min read
Primary sourceCity of Phoenix Residential Process Overview

You cannot pour a footing or frame a wall on a new Phoenix home until the city issues a building permit. The permit is the city's sign-off that your plans meet the adopted codes, your zoning, and any approved site conditions. This page walks the real steps: what you submit, how the package has to be put together, how the city reviews it, and what it takes to get the permit in hand.

What a residential permit requires

Phoenix runs new-home permits through its Planning and Development Department. For a new house, you submit your plans using the city's Residential Plan Submittal Plan Review Checklist so nothing required is missing. A complete single-family submittal includes:

  • A completed Construction Permit / Plan Review Application.
  • Two sets of plans and calculations, including the structural and energy work engineered for Arizona loads.
  • A plot plan showing the lot and the orientation of the house on the lot, with setbacks (the required distance from each property line) called out.
  • Energy code compliance paperwork, since Phoenix collects an Energy Code Compliance Certificate fee on residential work.

The city states the submittal step plainly:

The customer submits proposed building plans to the residential permit counter using the Residential Plan Submittal Plan Review Checklist, along with a completed Construction Permit / Plan Review Application. All submittals must include two sets of plans and calculations and a plot plan showing the lot and orientation of the house on the lot.

A package that is incomplete gets handed back before review starts, which costs you days. Note that grading, drainage, or hillside permits, if your lot needs them, must be obtained before the building permit can issue.

How review and issuance work

After you submit, staff checks the package for completeness and, if complete, collects the review fees. Then the formal review begins. Phoenix describes the core of it directly:

Staff reviews the plans for compliance with adopted city codes, design review requirements and any approved site plan conditions of approval. If corrections are required, staff will contact the customer to pick up the plans, make corrections and re-submit for review.

When the plans clear, the city notifies you that they are ready, you pay the permit fees, and the permit issues. So the flow is: submit a checklist-complete package, pay the review fee, pass plan review (with a correction loop if needed), then pay the permit fee and pick up the permit.

Here is a concrete example. Suppose you submit a 3,000 square foot custom home in Phoenix with a plot plan that shows the house 4 feet from the side property line where the zoning requires 5 feet. Staff flags the setback in plan review, contacts you to pick up the plans, and you shift the footprint or seek relief before re-submitting. That single correction round can add a week or two before the permit issues, which is why the plot plan setbacks are worth getting right the first time.

When this comes into play

This process governs the front end of every Phoenix build:

  • Build-on-your-lot. Your designer assembles the checklist-based package with the plot plan and engineered calculations, and the review clock runs through any correction rounds before the permit issues.
  • Owner-builder. If you pull the permit yourself instead of using a licensed contractor, you rely on Arizona's owner-builder exemption under A.R.S. 32-1121, which only covers a home you intend to occupy yourself, not one built for sale or rent within a year. That choice decides who signs the application and carries responsibility.
  • Resubmittals. If review finds corrections, you pick up the plans, fix the sheets, and re-submit. Each round adds calendar time, so a clean first submittal is the cheapest path.

What this means for you

Budget for the permit as a real line item, and split it in your head into the review fee (paid up front) and the permit fee (paid at issuance). Get the plot plan setbacks right the first time, because a setback violation is one of the most common reasons a residential plan gets corrected. Build review time into your schedule rather than assuming the permit is instant, and confirm whether you or your contractor is the permit holder, since that decides who signs the forms. If your lot is hillside or needs grading, line up those permits first, because they gate the building permit.

This entry sits between the codes and the field work in the Phoenix module. The standards your plans are checked against are listed in Phoenix Adopted Building Codes . Once the permit issues, the work gets verified through Phoenix Building Inspections for New Homes . For the full sequence of building a home, see the steps to building a custom home in Arizona .

Source

The submittal items, required plot plan, and review-to-issuance steps are published by the City of Phoenix: Residential Process Overview on phoenix.gov . For applications, checklists, and contacts, see Residential Projects .

This page is general information, not a substitute for the city's current checklist. Submittal items, fees, and timelines change, so confirm the live requirements with Phoenix Planning and Development before you file.

All City Building Codes
Desert landscape
Build With Us

Begin Your Build

Relax while we manage every detail, throughout the entire process. Tell us about your vision, and we'll be in touch to schedule a consultation.

How can we help?

Call usText us